Fully assembled wind turbine at Millour Hill Extension - 12th February

millourhill

This week saw the first turbine assembled in place on site at Millour Hill, with work now moving to assemble the second wind turbine.

Siemens construction personnel found a calm weather window in order to crane the parts into position for the 3 MW direct drive turbine.

Once the second turbine has been assembled, and the turbines commissioned, they will generate an extra 6.4 MW for Community Windpower's Millour Hill Wind Farm, supplying additional green energy for local Ayrshire homes.